THE PROJECT
Staged Roof Replacement Across An Occupied Townhouse Complex.
Scope
IRE Roofing is replacing hail-damaged roofs at a 22-townhouse complex in Holland Park West for an insurance repair builder. The works are being delivered in stages while residents remain on site. IRE is coordinating crane lifts and edge protection with the builder’s programme.
Staging Work Around Residents And Site Access
The crew completes one group of townhouses before moving to the next. That means sequencing deliveries, lifts and roofing works around resident access and other trades, with materials positioned for each stage.
With crane access through the adjoining park ruled out, IRE planned separate crane visits for staged material lifts. The aim was to limit how much material needed to be stored at any one time and reduce manual handling between work areas.
Outcome To Date
Stage 1 finished on 6 November 2026 and covered six townhouses. IRE sent progress and completion photos and supporting documentation to the builder. The remaining roof replacements are in progress.
Project Timeline
- Stage 1 complete
Roof replacement completed for six of the 22 townhouses.
- Crane lifts for material staging
Crane lifts helped position roofing materials for the next works.
- OngoingRemaining roof replacements
Works continue in stages, with crane access, edge protection and deliveries planned around residents and other trades.